How to write a sourcing brief a manufacturer can actually quote
Most slow supplier searches are slow because the first message could not be answered. This checklist shows what a manufacturer needs to confirm interest and quote — files, tolerances, material standards, quantities — what can be added later, and how to keep confidential information out of the first round.
The minimum a manufacturer needs
- What it is — product or component, and what it is used for.
- How it is made — process (machining, injection moulding, stamping, moulded rubber, assembly) and material, as far as you know.
- How many — quantity per order and estimated annual volume; say if it is a one-off project or recurring supply.
- What must be true — critical tolerances, surface finish, standards, documentation and any regulatory requirement.
- When — target dates for samples and first delivery.
- Who decides — the person who will evaluate quotations and samples on your side.
What a quotable technical package looks like
For machined, moulded and stamped parts, the package that lets a Portuguese shop quote without a round of questions is well established:
- 3D model in STEP (AP214 or AP242) and a 2D drawing in PDF with dimensions, tolerances and the revision number on every sheet (Makerverse RFQ guide).
- General tolerances: if the drawing does not specify them, state the class — ISO 2768-1 (f/m/c/v for linear and angular) and ISO 2768-2 (H/K/L for geometry). European shops default to “ISO 2768-mK” when the drawing is silent (Shapeways reference); if you need tighter, say where.
- Material by European standard: EN/ISO grades are what Portuguese suppliers buy — S235JR or S355J2 rather than A36 or A572, EN AW-6082-T6 rather than 6061-T6, 1.4301 rather than 304. If you only have an ASTM reference, say “or equivalent” and let the supplier propose.
- Secondary operations: heat treatment, anodising, plating, painting, marking — each with its standard or acceptance criterion.
- For moulded parts: resin and grade (or “equivalent”), colour reference, cavities expected, tool life in shots, whether you want the moulder to make the tool, who owns it and where it is stored.
- For rubber: compound family (EPDM, NBR, silicone, FKM), hardness in Shore A, bonding to metal if any, and the test you will accept parts against.
What can wait for the second round
Full drawing packages for the whole assembly, packaging specifications, logistics details, contract terms and your supplier code of conduct can follow once a candidate has confirmed interest and basic fit. Sending everything at once to a long list of suppliers wastes their time and exposes your information unnecessarily. A good rhythm is: short brief to six to ten candidates, full package to the three or four that confirm interest and capability.
Confidential information
Describe the requirement without confidential drawings in the first message. Agree in writing how documents may be shared — with whom, for what purpose, and whether an NDA is needed — before sending them. Portuguese companies sign NDAs routinely; use your own template or a short mutual one under Portuguese or Swedish law, and name the people who may see the files. If you work through an intermediary, ask them to confirm that your brief will not be forwarded to suppliers without your authorisation.
Ask for a quotation you can compare
- Same drawing revision, material, tolerances, finish and quantities to every candidate.
- One-off costs (tooling, set-up, samples), unit price by quantity band, and freight shown separately.
- Lead time for samples and for series, and the assumptions behind them — tool trials, material availability, August shutdown.
- Documentation included with delivery: material certificates (EN 10204 type 2.2 or 3.1 for metals), inspection reports, certificates of conformity where applicable.
- Validity of the quotation (30 days is the norm; metal and resin prices move), currency, payment terms and the Incoterm — EXW, FCA or DAP, and from which address.
Tooling lead times are the item most often underestimated: industry sources put a typical injection mould at 8–12 weeks and often 14–16 after design loops and approvals (QualityInspection.org); prototype aluminium tools can be days (Protolabs). Ask for the tool lead time and the first-shot date as separate lines.
Quantities: say what you really expect
Minimum order quantities are set by tooling amortisation and set-up time, not by appetite. Benchmarks for injection moulding run at 500–3,000 units in China and 1,000–5,000 in Vietnam (Sourcify); European moulders with family or shared tools can go lower, and machine shops will quote from one piece upwards at a price that reflects it. Give three quantity bands — the first order, a typical repeat, and the annual total — and let the supplier show how price moves. An honest “annual volume unknown, first order 500, recurring if approved” gets a better quotation than an inflated forecast.
Regulated products
If the part is a medical device or goes into one, add to the brief: the device class you expect, whether the supplier or you will be the legal manufacturer, and the certificates you require (ISO 13485 scope, notified body certificate where applicable). The MDR guide for buyers explains why these three answers change the price.
A worked example (fictional)
The brief below is invented for illustration — the company, part and figures are not real — but its shape is what a Portuguese machine shop can quote from in one pass:
Part: housing for a hand-held measuring instrument, aluminium, machined from bar; 1 part number, STEP + PDF rev. C attached after NDA.
Material: EN AW-6082-T6 or equivalent; anodised natural, 10–15 µm.
Tolerances: ISO 2768-mK unless stated; two bores at H7, flatness 0.05 on the mounting face.
Quantities: first order 300; typical repeat 500; annual estimate 2,000 (unconfirmed).
Documentation: EN 10204 3.1 material certificate, first-article inspection report, CoC per delivery.
Timing: samples in 6 weeks, first delivery 10 weeks after sample approval; August shutdown to be stated.
Commercial: quote EXW and DAP Gothenburg, EUR, 30-day validity, proposed payment terms.
Decision: purchasing manager with the design engineer; comparison on total cost of the first year.
Eight lines, no confidential drawing, every question a quoting engineer would otherwise ask already answered.
Common mistakes that slow a search
- Sending the whole assembly drawing set to ten suppliers before any has confirmed interest.
- Leaving tolerances to the supplier’s default and discovering at first article that the default was not yours.
- Quoting ASTM grades without “or equivalent”, so the supplier has to source imported material.
- Asking for a single unit price without quantity bands, which hides where the tooling is amortised.
- Forgetting to ask for the tool lead time and the August shutdown, and then planning a product launch around a date nobody committed to.
- Not naming the decision-maker, so the supplier’s questions land in a shared mailbox.
Label what you know
A useful brief separates what is confirmed from what is assumed. The same discipline applies on the supplier side: when answers arrive, record each fact as confirmed, stated by the manufacturer, pending or not available. It keeps the comparison honest and makes the decision meeting shorter.
A simple template is available to download: sourcing brief template (text file). Where to send it is covered in the sourcing map of Portuguese industrial clusters.
Sources
Figures are quoted as published by the sources below, with their reference year. They describe the sector, not any individual company; capabilities and capacity are confirmed per project.
- Makerverse — what a CNC RFQ should contain
- ISO 2768 general tolerance classes
- Shapeways — ISO 2768-mK default
- EN vs ASTM steel grade equivalents
- Aalco — EN AW-6082-T6 datasheet
- QualityInspection.org — injection mould tooling lead times
- Protolabs — prototype tooling lead times
- Hubs — 30-day quotation validity
- Sourcify — MOQ benchmarks by country
Discuss your sourcing project
Fractio helps Nordic buyers search for manufacturers in Portugal and coordinates quotations, samples and follow-up from Scandinavia. Scope, responsibilities and remuneration are agreed before work starts; an enquiry is not an order.
Tell us what you need